Friday, December 28, 2007

Hallway Tile

The tile is 95% finished in the hallways. We weren't able to continue the hardwood flooring through these hallways because they are located on a cement slab. 3/4" plywood would have had to be place down before the 3/4" hardwoods were installed. This increase in height would have forced the stairs out of code. Anyway, we selected a tile that should tie in nicely with the wood floors. Once the hardwood is down the remaining trim tiles will be installed.

Laundry Room Cabinets

The laundry room is really starting to shape up nicely. The laundry cabinets are all installed and look great. The counter top still needs to be cut out so the wash sink can be installed The only other thing we are waiting on is the arrival (and installation) of the washer and dryer. Our contractor pointed out one small oops -- one of the larger cabinet doors actually hits one of the ceiling lights. Small oversight and something we are going to live with.

Wednesday, December 5, 2007

Along the tile road

After struggling with decision of what tile to put on the walls (that will remain for a long time!) for the first floor bathroom, we finally came to a decision. We picked a porcelain tile family that matched what we were looking for. The floor has a 13"x13" varied colored tile, which matches the 8"x8" on the walls of the tub/shower surround. We then selected a matching 2"x2" border flanked on both the top and bottom by a 1"x2" trim. The tile color contrasted nicely with the bisque tub and soap dishes. Master Bath is next!

Sunday, November 11, 2007

Drywall finishing

Well the drywall is hung and the finishers are going to town. It will be a number of days and a number of coats to smooth things out (something about an old, uneven house??) Anyway, it is looking more and more like it could become a home everyday. Drywall finishing Hoah!

Tuesday, November 6, 2007

coming together little by little

Well things are progrssing nicely now. The house is almost fully sided. The new downspouts were installed (now they match the siding) and the skylights were installed the roof was finally finished! The new septic system is all in and hooked up (along with the repair to the water main!)


















The drywall finishing is progressing nicely. We are beginning to have some issues with the heat in the house, so this week we are going to finish getting the furnaces installed and hopefully get the propane delivered. (there has been a problem thus far trying to get it, soon hopefully.)




We have been struggling with the wall colors but I believe we have nailed them all down. Paint is coming this weekend if all goes acording to plan.

Thursday, November 1, 2007

Drywall, Drywall, Drywall

Had to post these images this afternoon.
Was at the house this morning for the fainal rough electrical inspection (finally) and the drywall guys were going at it! It was amazing to see them working, like a well oiled machine. Shouting measurements, cutting, drilling trimming -- all at once. Absolutely amazing!

Tuesday, October 9, 2007

Siding?

Well it is official, it is starting to be put back together! Yesterday, the roofing materials and siding arrived. We had to use a 50 year shingle because of the close proximity to the water, and we chose to use a vinyl siding that has additional built in styrofoam insulation - CertainTeed Cedar Boards

Today, one half of the roof was shingled (we are waiting on the skylights to do the other side) and the siding started going up. We really hope we made the right decision regarding the color, but at this point it's a little too late for second guessing. In either case - it looks a heck of a lot better than the yellow!

Wednesday, October 3, 2007

Low batteries and new windows!

We finally got out to the house tonight to discuss switching and electrical requirements with the electrical contractor. It was also our first opportunity to see some of the new windows installed! The windows arrived yesterday but we were busy with the plumbing supply showroom picking out sinks and faucets to get to the house before dark. I was planning on taking a bunch of photos tonight but of course, after 2 shots the camera shut itself off due to low power. I was able to squeeze a few more shots out but not many.



























Unfortunately it looks like we are beginning to fall a little behind our original time line. The electrician doesn't think he will get through everything next week, which means no insulation the following week. The insulation contractor is booking 2 weeks out now, which means we will have to wait around until we can get scheduled once the electrician completes his work. :-/

More photos of the great progress coming tomorrow!

Saturday, September 22, 2007

Continual Improvement

Today the progress continued. Not only did the entire new roof get framed and sheeted in, we made some major decisions on the layout of walls in the first floor corridor and media room (you will have to wait for those photos but here are some of the roof.)

Friday, September 21, 2007

Onwards and Upwards

After deciding what we wanted to do (stick frame it all instead of the trusses) we had to place a quick order and keep our fingers crossed. Today the 'emergency' lumber arrived (big thanks to the supplier!) and away we went. There was a lot of time spent setting the one main LVL and then leveling out the studded wall. When we left this evening they were making great process. Plan was to begin sheeting before dark -- excited to see how far they got!

Wednesday, September 19, 2007

notice something wrong?

Yeah, it seems that the trusses are the wrong pitch, dimensions or something. Fun Day. (sorry for the dark photos - it was a long day and it was getting dark)

Monday, September 17, 2007

Will the destruction ever end?

Today we got our first peak at the project after being out of town for the weekend (Thanks - we had a great time!!!) What I expected to see was the new trusses that were in the driveway last week all framed up and a new roof on the bridges - not the case. I guess there was some heavy winds and rain while we were gone so construction of this sort was not safe.

Not one to sit idle (thank goodness!) The contractor and his team of "beat-things-downers" decided to lay into some of the other areas of he house that had yet to come down (exciting!!!) The wall between the office and the hallway was torn down, totally opening up the space.













The next exciting hole was the loss of the enclosing walls around the front stairwell. This really opened up the space and makes walking up the stairs less like walking into a tunnel. (Maybe a new skylight in here someday, hmmmmm.)











In contrast to the additional destruction we were happy to see the blown in insulation cover the exterior walls quite nicely.










And if the insulation wasn't enough -- we have 'some' floors!!










I wonder what tomorrow will bring...?

Tuesday, September 4, 2007

Three_way door, is no more...

Today we were back at the job site after a relaxing time away for the labor day holiday. There were some issues that came up while we were away that required a number of phone calls - but all is well.

The progress has been great. We met again with Kitchen Cabinet designer to go over some changes and specifics about what we want to see. That process will get underway as soon as the drywall is up in the kitchen so accurate measurements can be taken. We were very excited to see the the three-way (yeah, it was weird) is gone! In place of it we are going to have a nice welcoming open space
(check out the before and after photos. -> )

The walls for the powder room are all complete. It was an odd space. We will probably never know what the 2' tall tile walls were for but we are happy to cover them up.

Much much more to come, but it is really nice to start seeing some actual square walls coming together.

Tuesday, August 28, 2007

and then there were floors

Well a little flooring at least. Today the dining room was re-framed, moving the access to the basement into the corner, a much more out of the way location. Then some of the sub floor was laid down. Mind you it is a little, but a little is better than none making this a good sign.

The sub floor we are laying down supposedly has a 'limited' 50 year warranty. It it called Advantech Sheathing and is manufactured by Huber Engineered Woods. The overall cost was not much more than traditional board and this comes with an added piece of mind.

After checking out the work completed thus far, we decided to take a break from life and enjoy what we fel in love with when we first saw the place. We are looking forward to many, many more evenings like this.

Sunday, August 26, 2007

One wall at a time!

Today we were pleased to see our first new wall in place. After the contractor and the architect sorted out requirements and what needed to be put in place where, we are finally under way. This is our first new wall, between the media room and the living room. It is framed with 2x6s and will accommodate the double French doors that will come later on.

A few of the walls have been modified from 2x4s to 2x6s to provide increased support. Much of this increased support is needed to facilitate the large open areas we are looking to create. Many of the supporting beams have also been doubled or tripled up, providing the required support for the upcoming second floor.

The second wall is underway, but requires a little more care. a new beam will be installed across the entire span of the house. Because of this, removing the existing wall is a slower than normal process. Temporary support walls are put in place as sections of the existing wall/header are removed. This wall is about half way removed, should be finished up tomorrow.

Tuesday, August 21, 2007

Fireplace skinned

Well today was a another slow day. It seems there are some questions about the drawings so before any of the main support beams were set in place, some questions have to be answered. In the meantime, more of the new floor joists were set in place. The big deal is the the brick facade was torn (pounded) off. (sorry about all of the 'orbs' we are assuming they were there due to dust and not spirts. Well if they are spirts we hope they are friendly.) Our plan is to replace this brick with a custom stone veneer from Canyon Stone or a similar company. Tomorrow is another day. Hopefully the answers will come from the architect and we will be able to remove some of the load bearing walls blocking the wonderful view to the lake.

Monday, August 20, 2007

New wall (sorta)

Today things continued to move forward -- at a slow pace. A number of things were accomplished today, few of which provided visual evidence of anything being done. One thing that did take place construction wise today, was the the installation of a temporary support wall that allowed a load bearing wall to be removed, so it can be rebuilt.

The inspector stop by today and spoke briefly with the electrical and plumbing contractors. It seems everyone is on the same page and the inspector seemed pleased with what he saw (let's hope it stays that way!)

The electrical contractor has made a little more progress in taking pulling wires out in preparation for relocating the main panel and replacing it with a smaller sub-feed panel.

Saturday, August 18, 2007

New floor joists

Today we began to see a little progress -- a little. A large number of the floor joists that had been taken our to allow for the digging, began to be replaced. This process ended up taking a much longer time than originally planned. It seems the sill plate was basically gone - rotted away like a bad hunk of cheese. Treated lumber had not been used, so it had to be replaced. Once that was taken care of the joists started getting dropped in. Originally the floor had about a 1.5" difference in height due to going from the transition from one section of the house to another. This finally provides us a little solid floor to walk on. Nice.